Asphalt Paving at the Marina: August 23-25

Next Monday through Wednesday, August 23-25, IMCO General Construction and their paving subcontractor will be prepping and placing asphalt in various locations in the vicinity of the Marina Office and dry shed buildings.

Access to and use of the following locations will be prohibited all three days:
West dry shed – all units
East dry shed – all west facing and end units; east facing units and parking to the east of the shed will remain accessible
Dry shed launch
Marina Office parking lot – No parking except for Load/Unload Only (15 minutes maximum) in the north side of the lot; limited angle parking for Guest Moorage and N-Dock tenants will be available along Dock Avenue just north of the Marina Office lot.

There will be a short period of time on Wednesday, August 25, where vehicle traffic along Dock Avenue South between the CSR boatyard and the Marina Office will be detoured while asphalt is being placed. Dock Avenue will be closed to pedestrian traffic all day, Wednesday, August 25. Dock Avenue will remain open to pedestrians/vehicles at all other times during this three-day period. However, caution is urged due to increased construction-related traffic.

If you have any questions, please contact Doreen Torseth (206-794-5372) or the Marina Office (206-824-5700).  Thank you for your continued patience during construction!

Thursday, August 12, 2010

**UPDATE** No Fuel Sales FROM 9:30 A.M. TO 12:30 P.M. on August 17

**UPDATE** Tuesday's fuel shutdown will be from 9:30 a.m. to 12:30 p.m. only.

Due to fuel system upgrades, there will be no gas or diesel sales at the Fuel Dock on Tuesday, August 17, 2010.

Thursday, August 5, 2010

Extended Work Hours - August 9 through August 13

Good news! IMCO General Construction is close to completing the dredging work at the new travel lift bay between M- and N-Docks. As they will have met enough of their dredging goals for this week, IMCO will not be working tomorrow, Friday, August 6, or Saturday, August 7, as previously reported.

Beginning next week, IMCO will dredge and create a new rock slope in the guest moorage area of the Marina. In this particular area, tidal effects on the flowing sand subgrade will require them to schedule their work beginning each day when the tide is no higher than approximately +5’ MLLW and headed out. Therefore, IMCO General Construction has requested and received approval to work the following hours this coming week:
Monday, August 9, 7:00 am – 5:00 pm (regular hours)
Tuesday, August 10, 8:00 am – 6:00 pm
Wednesday, August 11, 10:00 am – 8:00 pm
Thursday, August 12, 10:00 am – 8:00 pm
Friday, August 13, 10:00 am – 8:00 pm (if needed)

Approval for the extended work hours included the following conditions:
1. The Contractor is required to comply with all noise requirements established by the City’s Municipal Code and WAC 173-60; and
2. Construction lighting shall be directed away from residential areas and is limited to lighting needed to safely illuminate the work zone as established by industry standards.

If you have any questions regarding the work to be performed or the extended hours the Contractor will be working, please don’t hesitate to contact Doreen Torseth or the Marina Office (206-824-5700).