Tuesday, November 23, 2010

No Construction Work at Marina Thanksgiving Week

Due to extreme weather and road conditions, there will be no construction work at Des Moines Marina this week.  IMCO General Construction Inc. and their subcontractors plan to be onsite again Monday, November 29.

Questions?  Please contact the Marina Office (206.824.5700) or Doreen Torseth (206.794.5372).

Wednesday, November 10, 2010

UPDATE: Dry Shed Launch Pier - Temporary Closure

UPDATE (Wednesday, November 17):
The dry shed sling launch will remain out of service a few more days in order to allow the new concrete sidewalk to harden further prior to allowing vehicle/trailer access to the launch pier.  If dry shed tenants would like to launch/retrieve a boat prior to Monday, November 22, please contact the Marina Office (206-824-5700).

Due to sidewalk construction along the bulkhead, the dry shed sling launch will be out of service from Thursday, November 11, through Tuesday, November 16.  If you have any questions, please contact the Marina Office (206-824-5700).

Guest Moorage/N-Dock Access Changes

Due to sidewalk construction along the bulkhead in front of the Marina Office, the existing guest moorage gangway will be removed Thursday, November 11.  Once the existing gangway has been removed, guest moorage and N-Dock tenants may access the docks via the new N-Dock security enclosure at the top of the bulkhead/just south of the dry shed sling launch pier.

Please contact the Marina Office (206-824-5700) or Doreen Torseth (206-794-5372) if you have questions or need assistance.

Tuesday, November 9, 2010

Project Status Update

“It’s starting to look less like a war zone and more like a marina again!” I can’t tell you how many times we have heard this comment or something similar from people walking by or through the Des Moines Marina this past month. And it is true; the final product is clearly taking shape.

Listed below are the highlights of the work performed by IMCO General Construction and their subcontractors during the month of October.

  • Installation and tensioning of the final four permanent ground anchors completed the structural elements of the new steel sheet pile/concrete pile cap bulkhead.
  • A single 63’ long steel guide pile was installed at the end of the L-Dock/Classic Yachts finger pier.
  • Assembly of the new guest moorage activity float was accomplished this past month. Three steel guide piles were installed along the east edge of this float system. New lighted power pedestals line the activity float’s east and west sides. A walkway along the center of the float is now open to allow access to the existing north guest moorage floats. The new 80 foot gangway was set in place at the north end of the activity float which will provide much easier access to the guest moorage area in all tidal conditions. Completion of the on-dock utilities and fire suppression system will take place in November.
  • At the top of the bulkhead above the guest moorage area, the new promenade is beginning to take shape. Two beautiful stamped concrete compass roses flanking the north and south ends of this area have been completed. Surrounding each of the compass roses are concrete multi-height seat walls. All along the bulkhead new lighting has been installed. In the next several weeks, work will be accomplished to tie this entire area together with sidewalks and landscaping. The new promenade area will soon provide a true gathering place for Marina visitors of all ages whether they arrive by water or by land.

Installation of sidewalks, irrigation, landscaping and asphalt paving will soon complete the North Marina Combined Projects body of work. Although several of these activities are weather-dependent, with bad weather potentially causing delayed completion of the activity, each week should find the area less occupied by construction equipment and looking again more like a marina.

Thank you for your continued patience throughout this past year of construction at the north end of the Des Moines Marina. Please be patient just a short while longer…. The final product will be worth it!

Thursday, November 4, 2010

Extended Work Hours Notification - Saturday, November 6

IMCO General Construction has received permission to perform tidally influenced work from 8:30 p.m., Saturday, November 6, through 12:30 a.m., Sunday, November 7.

The location of the tidally influenced work is at the new travel lift pier between M- and N-Docks.  The travel lift pier ladder has a stabilization brace that is to be welded to the steel pipe pile at an elevation of -2.0 feet MLLW.  In order to weld the brace, the tide must be lower than -2.0 feet for a period of several hours.  The low tide this coming Saturday night will be -2.9 feet MLLW at 11:51 p.m.

IMCO will have a project manager and welder onsite.  Equipment that will be used in this specific piece of work include a generator/welder unit and two work lights.

Approval for extended work hours include the following conditions:
  1. The Contractor is required to comply with all noise requirements established by the City's Municipal Code and WAC 173-60; and
  2. Construction lighting shall be directed away from the residential areas and limited to lighting needed to safely illuminate the work zone as established by industry standards.
Questions or concerns may be directed to Doreen Torseth (206-794-5372) or the Marina Office (206-824-5700).