- Underground utility duct banks constructed/conduit installed – done
- Existing traffic islands removed and new traffic islands/sidewalks constructed – done
- New concrete light pole bases formed and poured – done
- Asphalt paving repaired – done
Items yet to be completed include:
- Stripe entire North Parking Lot
- Install light poles (may be done after parking lot is re-opened)
Although the work was scheduled to be completed in time to have the Marina North Parking Lot open by May 8, inclement weather and subcontractor scheduling has delayed the completion date. IMCO General Construction now anticipates that the lot will re-open to vehicles on Friday, May 14. (This date is again subject to weather.)