Thursday, February 4, 2010

Construction Work at Marina N-Dock Ramp Area

ATTN:  Tenants of M-Dock and N-Dock:

IMCO General Construction is planning to install sheet pile in the area of the N-Dock ramp on TUESDAY, FEBRUARY 9, AND WEDNESDAY, FEBRUARY 10.  In order to accomplish the installation, the N-Dock ramp will be temporarity lifted/removed and power will be shut down to both M & N Docks.  Access to the M and N Docks will be via the guest moorage ramp and southward on the float to N Dock.  

The contractor anticipates that the necessary work can be completed in 1 1/2 to 2 days, however, please be aware that if unforeseen circumstances arise, the access restriction and scheduled power outage may extend to the following day.
If you have any concerns or require assistance in accessing the docks these two days, please call the Marina office at 206-824-5700 or contact any Marina employee.